Network Rail & Govia announce 18 Days of Rail Closures in 2018 & 2019

Rail passengers across Sussex are being urged to plan ahead as a ‘once-in-a-generation’ upgrade to the southern end of the Brighton Main Line was announced today by Network Rail and Govia Thameslink Railway (GTR).

The work in October 2018 and February 2019 is a key part of a £300m government-funded programme to tackle delay hotspots and boost the reliability of the railway in the south east, cutting delays and providing a better, more reliable rail service to the 300,000 passengers who travel on the Brighton Main Line each day.

From Saturday 20 to Sunday 28 October 2018 and from Saturday 16 to Sunday 24 February 2019, no trains will run between Three Bridges and Brighton or between Three Bridges and Lewes.

The unprecedented access provided by these planned closures will allow Network Rail engineers to renew and upgrade a stretch of railway that is responsible for more delays to Southern and Thameslink passengers than any other.

Please click on the link for more information.

https://www.networkrail.co.uk/feeds/passengers-advised-to-plan-ahead-as-brighton-main-line-rail-improvement-project-is-announced-for-october-2018-and-february-2019/

 

 

 

 

Advertisements
This entry was posted in Uncategorized. Bookmark the permalink.

Genuine enquiries by email please as we just can't reply to all comments.

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s